Mass Timber Giant
Our Challenge – Produce more than a kilometre of timber rafter beams for Red Stag’s new manufacturing plant – no problem for Techlam.
Designed to be 161 meters long by 61 metres wide and because of the long spans needed, timber was the obvious choice.
With 36 rafter beams measuring 31.3 meters each, plus various columns and other timber components, this large-scale project took a lot of planning from the get-go.
The logistics of running the massive volumes through our plant was an interesting challenge and we nailed it!
The Techlam Solution
As one of the largest timber buildings in the southern hemisphere, the finished manufacturing plant is impressive both in scale and finish. Techlam manufactured the components over a 7 month period (including 5 weeks of Level 4 lockdown). Our production team was phenomenal, cutting every member exactly to length on our factory floor – delivering the product to site for the construction team to seamlessly install. The finished structure contains a total of 1200m3 of Glulam, storing more than 255 tonnes of carbon.
Recent Articles

Timber Arch Sets Record for Size

Introducing Digibuild

Affordable Housing in CLT Looks Grand!

(Japan) Ingenious Element for Fire Design for CLT

Going up: Sydney Tall Timber Building Underway – Atlassian Central

US Army Mandates Mass Timber Consideration

Mass Timber for New Airport Terminal Sourced Locally

NEW: UK resource for fire safety engineering

Mass Timber Apartments by Enovate for K-O